| MileStone Status | Date | Amount | MB |
1
| Foundation Level Completed | 16/06/2020 | 2,195,120.00 |
|
2
| Plinth Level Completed | 28/09/2020 | 4,377,055.00 |
|
3
| First Floor Completed | 11/01/2021 | 2,414,729.00 |
|
4
| Second Floor Completed | 06/08/2021 | 6,953,092.00 |
|
5
| Finishing of Main Building | 26/08/2021 | 6,953,092.00 |
|
6
| Residential Block With Toilet Completed | 30/09/2021 | 0.00 |
|
7
| CSC Centre | 02/09/2021 | 0.00 |
|
| | Total | 22,893,088.00 | |