| MileStone Status | Date | Amount | MB |
1
| Foundation Level Completed | 17/01/2020 | 1,737,402.00 |
|
2
| Plinth Level Completed | 08/02/2020 | 700,000.00 |
|
3
| First Floor Completed | 22/02/2020 | 2,350,029.00 |
|
4
| Second Floor Completed | 04/04/2020 | 6,772,593.00 |
|
5
| Finishing of Main Building | 04/04/2020 | 7,328,571.00 |
|
6
| Residential Block With Toilet Completed | 04/04/2020 | 1,051,480.00 |
|
7
| CSC Centre | 04/04/2020 | 11,436,100.00 |
|
| | Total | 31,376,175.00 | |