| MileStone Status | Date | Amount | MB |
1
| Foundation Level Completed | 20/02/2020 | 1,415,629.00 |
|
2
| Plinth Level Completed | 15/03/2020 | 628,011.00 |
|
3
| First Floor Completed | 04/02/2020 | 3,295,991.00 |
|
4
| Second Floor Completed | 04/02/2020 | 1,051,490.00 |
|
5
| Finishing of Main Building | 19/02/2020 | 11,383,655.00 |
|
6
| Residential Block With Toilet Completed | 04/02/2020 | 1,051,490.00 |
|
7
| CSC Centre | 04/02/2020 | 3,295,991.00 |
|
| | Total | 22,122,257.00 | |