| MileStone Status | Date | Amount | MB |
1
| Foundation Level Completed | 27/01/2020 | 1,737,402.00 |
|
2
| Plinth Level Completed | 12/03/2020 | 700,000.00 |
|
3
| First Floor Completed | 08/05/2020 | 2,107,017.00 |
|
4
| Second Floor Completed | 13/08/2020 | 1,257,706.00 |
|
5
| Finishing of Main Building | 11/11/2019 | 11,442,400.00 |
|
6
| Residential Block With Toilet Completed | 11/11/2019 | 11,442,400.00 |
|
7
| CSC Centre | 11/11/2019 | 11,442,400.00 |
|
| | Total | 40,129,325.00 | |