| MileStone Status | Date | Amount | MB |
1
| Foundation Level Completed | 15/10/2020 | 2,642,532.00 |
|
2
| Plinth Level Completed | 13/01/2021 | 3,820,817.00 |
|
3
| First Floor Completed | 25/03/2021 | 5,938,178.00 |
|
4
| Second Floor Completed | 18/05/2020 | 7,424,143.00 |
|
5
| Finishing of Main Building | 27/07/2021 | 0.00 |
|
| | Total | 19,825,670.00 | |